Permits, contracts and money/UAE
Dispute with a renovation contractor in the UAE: where to go
What to do when a fit-out contractor leaves defects, stops work or asks for more money, and which body in Dubai actually hears the dispute, step by step.
A dispute with a renovation contractor in the UAE is settled through the contract and the courts, not through a complaints hotline. Dubai's consumer protection service lists contracting companies among the businesses it cannot act on. Send a written notice with a deadline first, and collect evidence. Then, for claims up to AED 500,000 in Dubai, file with the Centre for Amicable Settlement of Disputes at Dubai Courts. It tries to settle within 30 days, can appoint an expert before any court case, and a settlement it approves can be enforced like a judgment. If there is no settlement, the judge who supervises the centre decides the claim or sends it to court. Above that sum, or if the contract has an arbitration clause, see a lawyer.
#First: what kind of dispute is it?
| Problem | What the law gives you | First move |
|---|---|---|
| Defects during the works | Notice to correct within a reasonable time; then cancel or bring in another contractor at the first one's cost | Written notice with a list and deadline |
| Contractor stopped coming, or is so late they cannot finish on time | You may ask to end the contract at once, without a deadline, when the contractor clearly will not perform | Notice to return to site by a date; then end the contract under its termination clause or with a lawyer |
| Defects found after completion | The contractor answers for damage from their workmanship | Snag list with photos and a deadline (snag list) |
| "Extras" you did not approve | On a lump sum, changes are paid only if you caused or authorised them and agreed the price | Ask for the written approval they rely on |
| Quantities grew on a unit-rate job | The contractor had to warn you of the overrun with the expected increase | Ask when and how they warned you |
| Contractor damaged the building's common areas | Management claims against your deposit; you claim against the contractor | Photos, management's report, notice to the contractor |
#Step by step
- Collect the papers. Contract or signed quotation, the agreed scope, drawings and estimate, every written approval of a change, payment receipts, the contractor's trade licence (check the licence), photos and messages with dates.
- Stop the damage, not the evidence. Make the site safe, close water or power if needed, but do not demolish or cover anything in dispute before it is recorded.
- Send a written notice. To the company, not just the site foreman, by e-mail and to the address in the contract or licence. Name each defect or delay, what you want done, and a reasonable deadline. If you plan to cancel or bring in another contractor, say so.
- Get an independent view. A report from an independent engineer or inspector who did not work on the job turns "I think" into evidence. In Dubai you can also ask the Centre for Amicable Settlement to appoint an expert before any court case.
- Meet once with the facts. Many disputes end here when both sides look at the same list, photos and contract. Put any agreement in writing, with dates and amounts.
- File with the Centre for Amicable Settlement (Dubai, claims up to AED 500,000). It is part of Dubai Courts and works under a judge. A claim in its jurisdiction cannot be registered with the courts until it has been there first. Registration costs AED 250. It aims to settle within 30 days of appointing a conciliator, and that can be extended once. Limitation periods stop running from the day you register until the conciliation ends. A settlement approved there can be enforced like a judgment. If there is no settlement, the supervising judge decides the claim with a reasoned decision or refers it to the right court.
- Court for claims above AED 500,000, or when the centre's judge refers the case there. At this stage you need a lawyer.
Only if your contract has an arbitration clause: the dispute may have to go to arbitration instead of the courts. Read the clause and take legal advice before filing anywhere.
#Who does not handle it
- DET consumer protection. Its complaint page lists contracting companies and engineering consultancies as outside its scope, along with compensation claims and contracts between companies. If the firm is licensed for another activity, the portal's jurisdiction check decides.
- RERA. Its complaint system is for real estate companies, and it does not deal with financial claims, contract disputes or compensation.
- Building management. It can stop works that break the NOC and keep your deposit for damage, but it does not judge your contract with the contractor.
#Payments during a dispute
Under UAE law you pay on delivery unless the contract says otherwise. Most home contracts do say otherwise, with stage payments. So:
- Pay what the contract makes due for stages that are done and accepted.
- Hold back only what the contract allows, such as a retention, or the stage that is in dispute, and say in writing why.
- Do not pay ahead for work not yet done while the dispute is open.
- Keep every receipt. Cash with no receipt is hard to prove.
#Prevent the next one
Most renovation disputes start with something nobody wrote down: what exactly was in the price, which change was approved, what "finished" looks like. Read the contract checklist before you sign, and how to read an estimate before you compare prices. Planning the renovation in Librae removes much of the room for argument. Both sides see one agreed plan and one estimate, line by line. The contractor checks the plan on a free site visit before agreeing the price and schedule. They can propose a change, but cannot edit your plan, and every approval stays with you. The version you both agree is issued "For works" with a number, so a disputed "extra" is either in it or it is not. Contractors in the Librae directory are listed only after Librae checks their licence. In the UAE you can add independent quality control to a renovation ordered through Librae, so each stage is checked and defects surface before they become a dispute.
#What goes wrong
- Arguing only on WhatsApp with the foreman. Write to the company.
- Stopping all payments with no contract basis. The contractor then claims you are in breach.
- Hiring a new contractor before recording the defects and before giving notice. The first contractor will say the second caused the damage.
- Waiting. Evidence goes, memories blur, and limitation periods run.
- Assuming consumer protection will help and losing weeks.
- No independent report. Two opinions against each other rarely move anyone.
#How to check the work
- Contract, scope, estimate and approved changes in one folder.
- Contractor's trade licence and company details checked.
- Defects photographed with dates before anything is changed.
- Written notice sent to the company with a deadline.
- Independent report, or a CASD expert application, in hand.
- Payments made or held back only as the contract allows, with reasons in writing.
- Dispute clause read: court or arbitration.
- Claim filed with CASD (Dubai, up to AED 500,000) or with a lawyer's help.
#When to call a professional
- An independent engineer or inspector for a written report on defects, quantities or work done.
- A lawyer before cancelling the contract, before hiring another contractor at the first one's cost, for claims above AED 500,000, for arbitration clauses, and whenever cheques or fraud are involved.
- A leak-detection company or a DEWA-registered electrician when the dispute is about a leak or about the wiring.
#In the UAE
- Other emirates have their own courts and their own conciliation steps. Ask the emirate's courts or a lawyer before filing.
- Contracts signed before 1 June 2026 may still fall under the 1985 Civil Transactions Law, because the new one is not retroactive. The remedies are similar; which law applies is a lawyer's question.
- If the contractor damaged a neighbour's flat — a leak through the slab, for example — see leak from the flat above for who claims against whom.
#What the codes say
- UAE Civil Transactions Law (Federal Decree-Law 25/2025): notice to correct, cancellation and replacement contractor, Art. 818; liability for workmanship, Art. 819; payment on delivery, Art. 826; quantities and lump sums, Art. 828–829; no retroactive effect, Art. 4.
- Dubai Law No. 18 of 2021 (conciliation), as amended by Law No. 9 of 2025: settlement enforceable, Art. 6(e); 30 days and one extension, Art. 21(e); conciliation before court and the judge's decision if it fails, Art. 28(a) and 28(c); limitation suspended, Art. 29; AED 250 fee, Art. 30.
- Dubai Resolution No. 4 of 2025: CASD jurisdiction up to AED 500,000 and expert appointment before proceedings, Art. 1.
- DET Consumer Rights: eligible and ineligible complaints.
- Dubai Land Department, RVS: what RERA complaints exclude.
This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.
Sources
- Dubai Department of Economy and Tourism, Consumer Rights, Submit a complaint — Complaints against DET-licensed businesses about poor or incomplete services, warranty, delays and charges. Ineligible include contracting companies and engineering consultancy firms, compensation claims for damages, and contracts between companies. The portal checks jurisdiction.
- Federal Decree-Law No. 25 of 2025, UAE Civil Transactions Law, Art. 4, 818, 819, 826, 828, 829 — In force 1 June 2026, not retroactive (4). Notice to correct, then rescission or another contractor at the first one's cost; immediate rescission cases (818); liability for workmanship (819); payment on delivery unless agreed otherwise (826); price and variation rules (828, 829).
- Dubai Law No. 18 of 2021 Regulating Conciliation in the Emirate of Dubai, Art. 6, 21, 28, 29, 40 — Centre for Amicable Settlement of Disputes (CASD), conciliators under a judge (6); 30 days from appointing the conciliator, extendable once (21(e)); limitation suspended from registration until conciliation ends (29); supersedes Law 16 of 2009 (40). Articles 5, 6, 28 and 30 now read as amended by Law No. 9 of 2025.
- Dubai Law No. 9 of 2025 amending Law No. 18 of 2021 Regulating Conciliation, Art. 1 — In force from publication (issued 8 July 2025). New Art. 6(e) (settlement approved by the conciliator, enforceable once the executory formula is affixed), Art. 28 (such claims cannot be registered with the courts before the CASD; if no settlement, the supervising judge decides by reasoned decision or refers the claim to the competent court), Art. 30 (AED 250 registration fee).
- Dubai Resolution No. 4 of 2025 determining the disputes within the jurisdiction of the CASD, Art. 1 — Claims not exceeding AED 500,000; applications to appoint experts before proceedings; ratification of conciliation agreements regardless of value.
- Dubai Land Department, Complaint against a real estate company (RVS) — RERA complaints are against real estate companies and exclude financial claims, contract disputes and compensation.