Accepting a renovation: snag list room by room
How to inspect a finished renovation, write snags a contractor cannot argue with, and hold back payment until they are fixed, with notes for UAE flats.
Accepting a renovation means checking every room against a written list before the last payment. Walk the flat alone first, in daylight, with a torch, a long straightedge, a socket tester and your phone. Write each defect as room, item, problem and fix, with a photo. Then walk it again with the contractor, agree a date, re-check, and pay against a closed list. You can keep part of the money back for a defects period only if the contract says so, so write it in before work starts.
#Before the walk-through
Check the contract. UAE law says you pay on delivery unless you agreed otherwise. It also lets you pay stage by stage after each part is inspected and accepted. So anything extra — a retention, a defects period, an inspection before the last payment — must be in writing. Look for:
- the scope and drawings you approved, so "finished" has a meaning;
- what part of the price is tied to completion and what is held back;
- how long the contractor will come back for defects, and how fast;
- which certificates and documents you get at the end.
Pick the time. Daylight, after cleaning, with power, water and cooling on. Dust hides scratches, and a flat without power cannot be tested.
Bring:
- a strong torch;
- a 2 m straightedge or level (ask the contractor for theirs);
- a plug-in socket tester;
- a tape measure;
- a coin or a key to tap tiles;
- painter's tape to mark snags;
- your phone for photos.
If the job was planned and ordered through Librae, the scope and drawings are the version issued "For works" with its number. Walk the rooms against it: anything that differs is either a change you approved or a snag.
#How to write a snag
One line per defect, numbered:
| No. | Room | Item | Problem | Fix |
|---|---|---|---|---|
| 12 | Bathroom 2 | Wall tiles, left of basin | 3 tiles sound hollow, one cracked | Replace 3 tiles, match grout |
| 13 | Bedroom 1 | Door | Rubs the frame at the top when closing | Adjust hinges, door closes freely |
| 14 | Living room | Ceiling by the window | Board joint visible in daylight | Re-tape and sand, repaint whole ceiling |
Rules that save arguments:
- Location you can find again. Room, wall, distance from a corner. Put tape on the spot.
- What is wrong, not how you feel. "Gap 6 mm at skirting joint", not "skirting bad".
- What "fixed" means. Replace, adjust, repaint the whole wall. Repainting a patch on a matt wall often shows.
- Photo with the tape in it.
- Date and two names on the list. Yours and the contractor's site lead.
Send the list by e-mail or message the same day, so the date is on record.
#Room by room
#Walls and ceilings
- Look along each wall from one end with the torch held low. Bumps, waves and board joints show up as shadows.
- Then judge the paint the fair way: from 2 m away in daylight, with no lamp shone along the surface. That is how LABC Warranty, a UK new-home warranty provider, judges paintwork. A defect visible only with a torch held flat is hard to win.
- Straightedge test. LABC allows up to ±5 mm under a 2 m straightedge and no sharp step over 4 mm in 300 mm. Plumb: up to 10 mm out in a storey height. This is a published yardstick, not UAE law, but a contractor will find it hard to argue with.
- Cracks up to 3 mm wide where walls meet ceilings and floors can come from shrinkage. LABC says they may appear; ask for them to be filled and painted, not for the wall to be rebuilt.
- Paint: even colour, no patches, no roller marks; what a good paint job looks like is in painting walls.
- Ceiling access panels open, and the fan coil behind them can be reached. See the FCU guide and plasterboard ceilings.
#Floors and tiles
- Tap every tile. Hollow sounds, steps between tiles, uneven joints and grout: check them as in checking finished tiling.
- Level: LABC allows 4 mm per metre on floors up to 6 m across. A 2 m straightedge laid in several directions shows dips and humps.
- Wood and vinyl: gaps at the walls hidden under skirting, no lifting or clicking at joints, door bottoms clear the floor (vinyl, engineered wood).
- Silicone, not grout, where floor meets wall, bath or shower tray.
#Bathrooms and kitchen
- Run every tap hot and cold for a few minutes. Look under basins and sinks with the torch for drips at every joint.
- Fill the basin and the shower floor, then drain. Water should leave without pooling. On a walk-in shower, pour water at the far corner and watch it reach the drain.
- Flush each WC twice. Check the cistern stops filling.
- Ask for the waterproofing record: when it was laid and how it was flood-tested (waterproofing and flood test).
- Ask for the pressure test record on new pipes (pressure testing).
- Grout should be full and even (grout types), silicone neat and continuous.
- Kitchen: doors and drawers aligned with even gaps, no step where worktops meet, appliances run.
#Electrics
- Test every socket with the plug-in tester. Every switch, every light, every dimmer.
- Press the test button on each RCD in the board. It must trip.
- The board is labelled circuit by circuit.
- Get the electrician's test certificate. What it must contain is in electrical testing after a renovation.
#Doors and windows
- Each door opens and closes freely, latches, does not rub. LABC allows up to 5 mm distortion across a door and 9 mm over its height, and up to 5 mm gap at the head.
- Factory-painted frames: no visible scratches from half a metre.
- Glass: look from 3 m in daylight. Scratches you see only from close up do not count under the LABC rule.
#AC and ventilation
- Each thermostat switches its unit, the fan changes speed, the room cools.
- Grilles clean, straight, not painted over.
- Bathroom extract fans run and pull a sheet of paper.
#After the walk-through
- Agree the list and a date with the contractor's site lead. Both sign or confirm by message.
- Re-inspect only the list. Tick off what is fixed, add anything the repairs damaged.
- Collect the paperwork before the last payment: electrical test certificate, pressure and flood test records, warranties for appliances and fittings, drawings of where pipes and cables now run, spare tiles and paint codes.
- Pay against the closed list. Keep the retention, if your contract has one, until the end of the defects period.
- UAE flats: management's check. Building management also inspects before it returns your deposit. Dubai Holding Community Management, for example, asks you to report completion with plans of new services, inspects within about 21 days and gives 30 days to fix anything that does not match the approval. Ask your management how they do it (see renovation permits in Dubai).
If the contractor ignores the list, send a written notice with a deadline. While the work is still under way, UAE law lets you demand that defective work be fixed within a reasonable time; if it is not, and once the defect is established, you may cancel the contract or have another contractor fix it at the first one's cost. The contractor also answers for damage caused by their workmanship. Either step needs a lawyer. Keep the dated list, photos and messages.
#What goes wrong
- Paying in full on a verbal promise. The snags then wait for months.
- A vague list. "Paint not good" cannot be fixed or checked.
- Inspecting at night under downlights. Grazing light makes every wall look bad, and dust hides real defects.
- Patch-painting one spot on a matt wall. It flashes. Ask for the whole wall.
- Forgetting what you cannot see later. Pressure, flood and electrical test records must be asked for before the walls and ceilings are closed, not at the end. See order of works.
- Accepting a new ceiling with no access to the fan coil or valves.
- Unapproved changes in a flat still under the developer's warranty. Emaar warns that works outside the approved scope can cost you the defect liability warranty.
#How to check the work
- Contract says what is held back, for how long, and what documents you get.
- Every room walked in daylight; snags numbered, located, photographed.
- List sent to the contractor in writing, with a date for fixes.
- Every tap, drain, WC, socket, light, RCD, door, window and AC unit tried.
- Electrical certificate, pressure and flood test records in hand.
- Warranties, drawings of hidden services, spare tiles and paint codes in hand.
- Re-inspection done; list closed and signed.
- Management's completion check booked; deposit refund requested.
#When to call a professional
- An electrician to test and certify if your contractor's electrician did not; in the UAE, a contractor registered with the utility (DEWA in Dubai).
- A plumber or leak-detection company if you see damp, stains, falling pressure or a running meter with all taps closed.
- A snagging or building surveyor for a large villa renovation, or when you and the contractor disagree about what is acceptable.
- A structural engineer if a crack is wider than 3 mm, grows, or runs across a wall rather than along a junction.
- A lawyer before cancelling the contract or hiring someone else at the contractor's cost.
#In the UAE
- Two inspections end a renovation in a tower flat: yours with the contractor, and management's against the NOC. The deposit comes back after the second (see developer NOCs).
- If your flat is new and still within the developer's warranty, your renovation snags and the developer's snags are separate lists. Fix the developer's first; see handover of a new apartment.
- Where an engineer designed the work and the contractor built it, UAE law makes them jointly liable for 10 years from delivery for collapse and for defects that threaten the structure or safety. Ordinary finishing defects are a matter for your contract. Claims under the 10-year rule must be brought within 3 years of finding the defect.
#What the codes say
- UAE Civil Transactions Law (Federal Decree-Law 25/2025), in force 1 June 2026, not retroactive: standard of work and notice to fix defects, Art. 818; liability for workmanship, Art. 819; 10-year liability, Art. 821; 3-year limit for claims, Art. 824; taking delivery and payment, Art. 825–827. Work done under a contract from before that date may still fall under the 1985 law (10-year liability in Art. 880).
- LABC Warranty Technical Manual, Section 1 Tolerances: walls, ceilings and plumb, 1.1.3; floors, doors, windows and glass, 1.1.4; paint, joinery and fitted furniture, 1.1.5.
- Dubai Holding Community Management rules (2026): completion notice and inspection, §8.1.40.
- Emaar Home Modifications fact sheet (2022): consequences of unapproved works.
This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.
Sources
- Federal Decree-Law No. 25 of 2025, UAE Civil Transactions Law, Art. 818, 819, 821, 824–827 — In force 1 June 2026, not retroactive (Art. 4). Work to the contract or recognised professional standards; if defective work shows during the work, notice to correct it, then rescission or another contractor at the first one's cost (818); liability for workmanship (819); 10-year liability for collapse and defects threatening structure and safety, from delivery (821); claims within 3 years of discovery (824); duty to take delivery, payment on delivery, part payments after inspection and acceptance unless agreed otherwise (825–827).
- LABC Warranty, Technical Manual, Section 1 Tolerances (2021) — UK new-build warranty yardstick. Walls and ceilings ±5 mm under 2 m straightedge, no step over 4 mm in 300 mm, plumb 10 mm per storey (1.1.3); floors 4 mm per metre up to 6 m; door distortion 5 mm across, 9 mm in height, head gap 5 mm; frames from 0.5 m, glass from 3 m (1.1.4); paint from 2 m in daylight; fitted furniture and worktops (1.1.5).
- Dubai Holding Community Management, Community Rules and Regulations, 1 October 2026, §8.1.40 — Owner notifies completion with plans of new services; management inspects within about 21 days; non-compliance fixed within 30 days.
- Emaar, Home Modifications fact sheet (2022) — Works carried out without following the guidelines may mean loss of the defect liability warranty, resale and title deed problems, and violation notices.