Inspection and handover/UAE
New apartment handover in the UAE: snagging and defects liability
What to check before you take the keys from a UAE developer, how to record snags, and how long the developer must fix defects under Dubai and UAE law.
Before you collect the keys to a new flat, inspect it with the developer's representative and get every defect on a signed snag list. In Dubai the developer then has to repair or replace faulty installations for 1 year from handover of your unit, and fix structural defects for 10 years from the building's completion certificate. A contract cannot shorten either period. Do the inspection with power, water and cooling on, re-inspect after the fixes, and hold off on renovation until the developer's list is closed and your NOC is issued.
#How handover usually goes
- Handover notice. The developer tells you the building is complete and what to pay and bring. Read the purchase agreement (SPA) clause on handover and defects at the same time.
- Book the inspection. Ask whether power, water and cooling will be on. Without them you cannot test sockets, taps, drains or AC, and you inspect only half the flat.
- Inspect with the developer's representative. Many buyers also hire a snagging company. You do not have to; below is what you can check yourself.
- Snag list. Every defect goes on the developer's form or your own report, with photos. Both sides sign or confirm it in writing. Ask for a date for the fixes.
- Re-inspect, if the developer fixes before handover. Check only the list, plus anything the repairs damaged. Many developers hand over the keys first and fix the snags afterwards; then the signed list is your record, and you re-inspect when they say the work is done.
- Sign and collect the keys. Read the handover form. If it says you accept the unit in good condition, attach or refer to the snag list that is still open.
- Accounts and moving in. DEWA, cooling provider, building access. From this date the 1-year period for installations runs.
- Defects found later. Report them in writing to the developer's customer service while the period runs, with photos and dates.
#What the law gives you
| Defect | Who answers | For how long | From when |
|---|---|---|---|
| Faulty installations: electrics, plumbing, drainage, AC and similar (Dubai) | Developer | 1 year | Handover of your unit |
| Structural defects (Dubai) | Developer | 10 years | Building's completion certificate |
| Collapse, or defects threatening structure or safety (UAE) | Engineer and contractor, jointly | 10 years | Delivery of the building |
What else the law says:
- Waiting does not help. If you refuse or delay taking possession, the 1-year period starts from the completion certificate anyway.
- The contract cannot cut these periods. Dubai law voids any agreement against these rules, and keeps any other rights you have. UAE law voids any clause that exempts or limits the 10-year liability.
- Claims under the 10-year rule must be brought within 3 years of the collapse or of finding the defect.
- Who you claim against. The federal rule binds the engineer and the contractor to whoever ordered the building, usually the developer. In Dubai your own claim for structural defects is against the developer, under the jointly owned property law.
- Finishes are a grey zone. A scratched door or uneven paint is neither an installation nor structure. Get it on the snag list before you sign; afterwards it is your word against the developer's.
- Outside Dubai the federal 10-year rule applies; for installations and finishes read your SPA and the emirate's property law, and ask a lawyer if it matters.
The UAE 10-year rule moved from the 1985 Civil Transactions Law to the new one on 1 June 2026. The new law is not retroactive, so a building delivered before that date may still fall under the old one. The periods are the same.
#What to check
Take a torch, a plug-in socket tester, a 2 m straightedge or level, a tape measure, a coin to tap tiles, painter's tape and your phone.
Front door and corridors
- Door closes, locks, seals; no damage to the frame.
- Intercom and doorbell work.
- Smoke detectors and sprinklers present and undamaged. Do not test them with smoke; that can call out Civil Defence (see smoke tests).
Walls, ceilings, floors
- Look along every wall and ceiling with the torch held low for waves and joints, then judge the paint from 2 m in daylight. That is how LABC Warranty, a UK new-home warranty provider, judges it.
- Straightedge: LABC allows up to ±5 mm under 2 m on walls and 4 mm per metre on floors. Use these as a yardstick, not as UAE law.
- Tap every tile. Hollow tiles, steps and grout: see checking finished tiling.
- Cracks up to 3 mm wide where walls meet ceilings and floors can come from shrinkage; they still go on the list to be filled and painted. Anything wider, growing, or running across a wall goes on the list and to the developer's engineer.
Doors, windows, glass, balcony
- Every door opens, closes and latches without rubbing.
- Windows and balcony doors slide and lock; seals continuous; no daylight through closed frames.
- Glass looked at from 3 m in daylight. Scratches on factory-finished frames should not show from half a metre.
- Balcony drain clear: pour a bucket of water and watch it go.
Bathrooms and kitchen
- Run every tap hot and cold. Look under every basin and sink with the torch.
- Fill and drain the basin, bath and shower floor. Water must not stand.
- Flush every WC twice; the cistern must stop filling.
- Silicone continuous around baths, trays, worktops.
- Water heater: no drips from the valve or the tray (see water heater above the ceiling).
- Kitchen units aligned, appliances run.
Electrics
- Every socket with the tester, every switch and light.
- Press the test button on each RCD in the board. It must trip.
- Circuits labelled. Ask whether the developer hands over test certificates; what they contain is in electrical testing.
AC
- Each thermostat switches its fan coil; the room cools; no water marks under the units.
- Access panels open (see fan coil units).
Documents
- Signed snag list, keys and access cards counted, appliance warranties, building rules, management's contact for NOCs.
#After the keys
- Report new defects in writing during the year, to the developer's customer service. Phone calls leave no date.
- Structure and common parts — cracks in structure, leaks from shared pipes, façade, lobby — also go to the building's management. The owners committee can take structural and urgent common-part defects to management or RERA.
- If the developer will not act. RERA's complaint system says it does not deal with contract disputes or money claims. A claim under your SPA or the law needs a lawyer. Keep the snag list, photos and every message.
- Renovating. Wait until the developer's list is closed. Then get the building's NOC first (see developer NOC for renovation). Emaar warns that works done without following its guidelines may cost you the defect liability warranty. When your own renovation is finished, accept it with a separate list (see accepting a renovation).
When you get to the renovation, start from the measured flat, not the brochure. Librae draws the plan from the developer's floor plan or an iPhone scan, with dimensions you confirm, so the areas of floors, walls and ceilings are those of the real rooms.
#What goes wrong
- Inspecting a flat with no power or water. Half the checks are impossible, and the faults appear after the keys.
- Signing "accepted in good condition" with snags open.
- A verbal promise to fix. No list, no date, no record.
- Waiting to take possession to stretch the warranty. In Dubai it starts from the completion certificate anyway.
- Starting fit-out on top of developer snags. Then nobody can tell whose work leaks.
- Testing smoke detectors with smoke.
#How to check the work
- SPA clause on handover and defects read.
- Inspection booked with power, water and cooling on.
- Every room checked with the list above.
- Snag list signed or confirmed by the developer, with a fix date.
- Fixes re-inspected, before signing or as soon as the developer reports them done.
- Handover form refers to the open snags.
- Handover date recorded: the 1-year period runs from it.
- Renovation planned only after snags are closed and the NOC is issued.
#When to call a professional
- A snagging company: if you are abroad, short of time, or the flat is large. Optional.
- The developer's engineer: any crack wider than 3 mm or running across a wall, damp patches, water under fan coils.
- A licensed electrician: if sockets or RCDs fail the simple tests.
- A property lawyer: before refusing handover, withholding payment, or starting a claim.
#What the codes say
- Dubai Law No. 6 of 2019: developer's liability, Art. 40; owners committee duties, Art. 24.
- UAE Civil Transactions Law (Federal Decree-Law 25/2025), in force 1 June 2026, not retroactive: 10-year liability, Art. 821; no exemptions, Art. 823; 3-year limit for claims, Art. 824. In the 1985 law: Art. 880, 882 and 883.
- Dubai Land Department, Real Estate Violations System: scope of RERA complaints.
- Emaar Home Modifications fact sheet (2022): loss of defect liability warranty for unapproved works.
- LABC Warranty Technical Manual, Section 1 Tolerances: yardstick for walls, floors, paint, doors and glass.
This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.
Sources
- Dubai Law No. 6 of 2019 on jointly owned real property, Art. 24 and 40 — Developer liable 10 years from the completion certificate for structural defects (40a); 1 year from handover of the unit for defective installations, from the completion certificate if the owner does not take possession (40b); other rights preserved (40c); contrary agreements void (40d). Owners committee reports structural and urgent common-part defects to management or RERA (24(6)).
- Federal Decree-Law No. 25 of 2025, UAE Civil Transactions Law, Art. 821, 823, 824 — In force 1 June 2026, not retroactive (Art. 4); it took over from the 1985 law, whose Art. 880, 882 and 883 held the same 10-year rule, the ban on exemptions and the 3-year limit. Engineer and contractor jointly liable 10 years from delivery for collapse and defects threatening structural integrity and safety (821); exemption clauses void (823); claims within 3 years of collapse or discovery (824).
- Dubai Land Department, Complaint against a real estate company (RVS) — RERA does not handle financial claims or disputes over contract terms; complaints about transactions older than 6 months are not considered.
- Emaar, Home Modifications fact sheet (2022) — Modifications not following the guidelines may lead to loss of the defect liability warranty, inability to resell or apply for a title deed, and violation notices.
- LABC Warranty, Technical Manual, Section 1 Tolerances (2021) — UK new-build warranty yardstick used for what counts as a defect. Walls ±5 mm under 2 m straightedge; floors 4 mm per metre; paint judged from 2 m in daylight; glass from 3 m; frames from 0.5 m; shrinkage cracks up to 3 mm at junctions.