Developer NOC for renovation in Dubai: Emaar, Nakheel, DAMAC, wasl
Where to apply for a renovation NOC in Dubai, what each developer or management company asks for, published fees and timings, and how to get the deposit back.
To renovate inside a Dubai flat or villa, you need a no-objection certificate (NOC) from whoever manages your community or building. Emaar, the Dubai Holding communities (Nakheel, Meraas, Dubai Properties, Meydan), DAMAC and wasl each have their own channel, fees and deposit. Most other developers hand their towers to a management company, and the NOC comes from that company. For the full approval path, and the rare jobs where the authorities step in, see renovation permits for an apartment in Dubai.
#Who issues the NOC: quick comparison
| Who runs it | Where you apply | Published timing | Published fees | Deposit |
|---|---|---|---|---|
| Emaar Community Management | Community portal from ecm.ae, "Home Modifications" | 3 business days (2022) | AED 1,000 or 2,000 in total, incl. 500 for review (2022) | Refundable, depends on the works; shown in the portal |
| Dubai Holding communities | Developer NOC, then a permit in the community app | Meraas: 2–3 working days minor, 10 major | Meraas minor works free | Mentioned in the rules, no amount |
| DAMAC | DAMAC Living app, "NOC for Fit Out/Alterations" | Work permit 2 working days | Shown in the app | Yes, amount in the app |
| wasl (freehold) | E-mail to freeholdnoc@wasl.ae | 2 working days minor, 7–21 days major | Told during review | Yes, back after completion papers |
| Independent management company | Its office or FM desk | Not published | Not published | Ask for it in writing |
All of them want roughly the same papers: a scope of works, your contractor's Dubai trade licence, photos or drawings of what changes, and proof that you own the unit. A tenant needs the landlord's written consent first; see renovating a rented flat.
#Emaar Community Management
- Get your contractor's papers first. Emaar's checklist starts with the contractor's or consultant's Dubai trade licence, so choose the company before you apply.
- Log into your community portal from ecm.ae, choose the property, then Home Modifications and "Apply for new home modifications". The service covers all Emaar communities except Burj Khalifa, Emirates Hills and Dubai Hills plots.
- Upload the checklist: the trade licence, a detailed scope, current photos of the areas, and proposed plans, sections or 3D views if the layout changes.
- Answer the reviewer on the portal; questions also arrive by e-mail.
- Pay and download the NOC. The 2022 fact sheet charged AED 500 for review, counted towards AED 1,000 for minor or AED 2,000 for major works, all non-refundable, and promised 3 business days from complete documents. Emaar also takes a refundable deposit, which covers damage to common areas. The amount depends on the works, and the portal shows it next to the fee; Emaar's current pages give no figure. Its older, undated FAQ, from before the current portal, gave AED 5,000 for villa alterations and no figure for flats.
- Only if the NOC or the reviewer asks for it: authority approvals from Dubai Municipality, DDA or Civil Defence, obtained by your contractor or consultant before work starts. Emaar lists this step "if required"; a cosmetic kitchen or bathroom refit inside the flat normally goes ahead on the Emaar NOC alone.
- Contractor permit. The contractor registers on ecmpermits.ae and applies for a Home Modification Permit with the NOC reference number e-mailed after approval. Approval takes one business day. Every contractor needs an entry permit, even for work that needs no NOC.
- Keep the NOC on site during the works, and keep it with the property papers afterwards for a future buyer. Emaar's 2026 Downtown rules require both.
No NOC is needed for internal painting, furniture, light fittings and regular maintenance. In apartments Emaar does not allow structural work, wall removal, taking up the original tiles (new tiles go over them), or moving or covering MEP and fire-fighting systems. If a previous occupant has already replaced the original tiles, Emaar can let you take up theirs: say so in the application and get a no-objection letter from the neighbours below. Its Downtown rules also want prior approval for new plumbing fixtures, rerouted pipes and new or changed AC units, and limit power tools to 9:00–13:00 and 15:00–17:00.
#Nakheel, Meraas, Dubai Properties and Meydan
These communities are now run by one company, Dubai Holding Community Management. There are two approvals: the developer's NOC and the community manager's work permit.
Many towers in these master communities, for example in JVC, JVT or Business Bay, were built by other developers and are run by their own management company. If your service-charge invoice comes from such a company, start with it, as described below, and ask whether the master developer's NOC is needed too.
Minor works are non-structural jobs inside the unit that do not touch the façade or common areas.
- A one-day job (handyman, AC service, pest control, internet) gets same-day access.
- Anything longer needs a Minor Modifications Permit, applied for in the community app. It is valid for up to 7 days unless the manager agrees to more.
- In Meraas communities a minor NOC is requested through RealConnect or Dubai Community Management; the permit comes the same day, the NOC in 2–3 working days, free of charge. Owner, tenant or contractor may apply.
Major works follow a stricter order.
- Developer NOC. Nakheel: Urban Planning, through the Nakheel website or My Nakheel app. Meraas: 800Meraas or customersupport@meraas.ae, with an owner's request letter, appointment and undertaking letters, title deed, passport, visa and Emirates ID, and existing and proposed plans; about 10 working days, administrative fee. The NOC is not processed until fees and documents are in.
- Authority approvals, only where the scope needs them, at your cost. In Nakheel communities under Trakhees, finishes, painting, flooring over the existing slab, replacing internal doors and drywall partitions up to 1.8 m need no Trakhees permit. Where the work does need a Trakhees NOC (construction, modification, extension), the contractor's long-term access pass needs both the Nakheel and the Trakhees NOC and costs AED 52.50 per worker.
- Major Modifications Work Permit from the community manager, with a copy of insurance for the works.
- Finish within the set period, never more than 6 months. Overrunning or changing the scope needs a new application.
Work hours are Monday to Saturday 8:00–18:00 (major works: weekdays), noisy work only 9:00–13:00 and 15:00–17:00, nothing on Sundays or public holidays.
#DAMAC
Apply in the DAMAC Living app under "NOC for Fit Out/Alterations": submit details, pay, wait for approval. The app shows the documents and payments for your type of work. The fit-out form asks for the owner's passport and title deed or SPA, the contractor's trade licence and third-party insurance, the fit-out fee, a security deposit, an undertaking and the owner's authorisation letter for the contractor.
A tenant can start the request; the owner then approves or rejects it in the app. After the NOC, the contractor needs a work permit from the building's FM team, normally within 2 working days. DAMAC's 2026 building rules also say, in general terms, that works need Dubai Municipality approval before they start. Do not file anything with the Municipality on your own: the app lists the documents for your type of work, and if it asks for an authority approval, your contractor or consultant obtains it. If unsure, ask DAMAC in writing before work starts.
#wasl freehold buildings
E-mail freeholdnoc@wasl.ae with the scope, title deed, passport and Emirates ID, and existing and proposed layouts. wasl answers within 24–48 working hours. A minor NOC takes 2 working days, a major one 7–21 days. The team tells you the fee and the deposit, e-mails the NOC after payment, and then you apply for access permits for the workers.
#Towers run by an independent management company
Developers such as Select Group, Azizi, Danube and Binghatti publish no modification process for completed buildings. There the building is run by a management company approved by RERA: Select Group, for one, lists Kingfield, Kaizen, SAGA, Provis and Strata Global for its towers. The same applies to most towers inside big master communities such as JVC or Business Bay.
To find out who manages yours:
- look at the service-charge invoice: it comes through the Land Department's Mollak system from the management company;
- ask reception or security, who deal with contractor passes every day.
Then ask them in writing for:
- the fit-out or modification guidelines and the application form;
- the fee, the deposit amount and how the deposit is refunded;
- insurance they require from you or the contractor;
- working hours, lift booking and debris rules;
- whether the master developer's NOC is needed as well, if the tower sits inside a master community.
None of these companies publish fees or deposits, so do not rely on figures from blogs.
#Getting the deposit back
Few managers publish how the refund works:
- wasl: e-mail the completion certificates to freeholdnoc@wasl.ae with the account holder's name, bank, branch, account number, IBAN and SWIFT.
- Dubai Holding communities: report completion with as-built plans of any new services. The manager inspects within about 21 days; defects must be fixed within 30 days. The rules do not describe the refund itself, so ask when you pay.
- Emaar: when the work is finished and the debris cleared, apply to Emaar for a completion inspection. If the work matches the NOC, the deposit comes back. Emaar's older FAQ gave two years from payment to apply, after which the deposit was forfeited; check the deadline in your NOC terms.
- DAMAC and management companies: ask for the refund procedure when you pay the deposit.
Why deposits get held back (all of it is in the rules above):
- Damage to common areas. Dubai Holding's rules allow deductions for damage by your contractor; Emaar charges repairs to the owner.
- Work that differs from the NOC. Unapproved work must be removed, within 30 days of notice in Dubai Holding communities.
- Overrunning the permit, which brings a non-compliance notice and a fee in Dubai Holding communities.
- Missing completion papers, such as wasl's completion certificates.
#What goes wrong
- Applying to the developer when a management company runs the tower. No answer comes. Check who sends the service-charge invoice first.
- Treating one manager's numbers as universal. Emaar's 3 days and wasl's 7–21 days apply only to them.
- Letting the 7-day minor permit lapse. In Dubai Holding communities a longer job needs a new permit, or the crew is stopped at the gate.
- Changing the scope mid-job. A new bathroom layout or extra AC unit needs a new application.
- No photos of the corridor and lift. If management deducts for damage, you have nothing to show it was there before.
- Losing the deposit receipt. wasl and others refund against your payment details and completion papers.
#How to check
Before work starts:
- You know who manages the building and have its current guidelines.
- NOC issued for your exact scope; validity date noted.
- Contractor permit or work permit approved; insurance given if asked.
- Deposit receipt and refund procedure saved.
- Dated photos of the corridor, lift and lobby.
At completion:
- What was built matches the NOC.
- Completion reported in writing, with as-built plans if asked.
- Common areas photographed again.
- Refund requested in writing with bank details.
#When to call a professional
- Drawings for major works: a Dubai-licensed consultant or contractor. Emaar's checklist starts with their trade licence.
- Structural or façade changes: ask management first whether they are allowed at all. They also need the master developer, the Land Department and the permitting authority.
- A deduction you think is unfair: ask management for the inspection report in writing. Disputes between owners and management go to the Rental Disputes Settlement Centre.
Almost every NOC package comes down to three things: a licensed contractor, a scope of works and layouts. In Librae the layouts before and after come out of one project, in 2D and with a 3D view if management asks for one. The licence is the part Librae checks itself: a contractor appears in its directory only once the licence and its validity have been verified.
#What the rules say
- Law No. 6 of 2019 (jointly owned property), Art. 16: owners and tenants must follow the building management regulation and the master community declaration; that gives building fit-out rules their force. Art. 39: substantial changes to the structure or external appearance need the master developer, the Land Department and the permitting authority.
- Emaar Home Modifications fact sheet 2022: steps, fees, timing, apartment prohibitions, entry permit for every contractor.
- Emaar FAQ (current): why the deposit is taken and that it is refunded after inspection. Emaar's older FAQ: AED 5,000 deposit for villa alterations and two years to apply for the refund.
- Emaar Downtown Dubai rules 2026, §4.1, §7.8, §7.9, §9.7.
- Dubai Holding Community Rules, 01.10.2026: §2.3.3.2 (deposit deductions), §8.1 (major works), §8.2 (minor works).
- DAMAC Community Rules for Residential Buildings, §7.4.
Fees, timings and rules change. We checked the documents listed in the sources on 31.10–01.11.2026. Your manager's current guidelines and the terms of your NOC come first.
This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.
Sources
- Emaar Community Management, Home Modifications fact sheet (2022, footer "Version 1 12-20210412"), archived copy — portal steps, works without NOC, apartment prohibitions, 3 business days, fees, authority approvals if required, entry permit for every contractor, consequences of unapproved works, checklist
- Emaar, FAQ, Home Modifications and NOC (read 01.11.2026) — deposit protects common areas against contractor damage; refunded after a successful completion inspection; no amount given
- Emaar, older properties FAQ, alterations (undated, e-Services era; read 01.11.2026) — villa alterations, AED 1,000 or 2,000 non-refundable charge by scope plus AED 5,000 refundable deposit; inspection after completion; refund to be applied for within 2 years of payment or forfeited
- Emaar Community Management, contractor permit fact sheet (ecmpermits.ae) — contractor registration, home modification permit with the NOC reference, one business day
- Emaar, Formal Rules and Regulations, vertical communities, Downtown Dubai (January 2026), archived copy — §4.1(vii) power-tool hours; §7.8, §7.9 approval for plumbing and AC changes; §9.7 NOC on display and kept, fire alarm protection, owner responsible for contractors
- Emaar Community Management, Downtown Dubai guidelines (archived 16.05.2026) — damage to common areas charged to the owner
- Dubai Holding Community Management, Community Rules and Regulations (01.10.2026, v3), chapter 8 — §2.3.3.2 deductions from the security deposit; §8.1 major works (developer NOC first, 6 months, insurance, removal within 30 days, completion and inspection in about 21 days, 30 days to remedy); §8.2 minor works (same-day access, 7-day permit, hours)
- Dubai Holding Community Management, communities list (read 31.10.2026) — Nakheel, Meraas, Dubai Properties and Meydan communities under one manager
- Meraas, FAQ, Major and Minor Modifications (read 01.11.2026) — 800Meraas for major works, documents, 10 working days, admin fee; RealConnect for minor works, same-day permit, NOC in 2–3 working days, free, owner or tenant may apply
- Nakheel, contact us and FAQ (read 31.10.2026) — Urban Planning NOC via website or My Nakheel app; contractor access for modification work needs Nakheel and Trakhees NOC and AED 52.50 per person
- DAMAC Living, fit-out work authorisation form and work permit guide (DAMAC Properties) — owner's passport, title deed or SPA, contractor licence and third-party insurance, fit-out fee and security deposit, undertaking, authorisation letter; FM work permit, 2 working days (work-permit.pdf)
- DAMAC, Community Rules for Residential Buildings (2026), §7.4 — prior written authorisation of OA management or developer and authorities; works approved by Dubai Municipality before they start
- wasl help centre, NOC for home improvements, fit-out works or modifications (read 01.11.2026) — freeholdnoc@wasl.ae, documents, minor 2 working days, major 7–21 days, fees advised by the team, access permit, deposit refund after completion certificates with bank details
- Select Group customer care, owners association contact details (read 31.10.2026) — buildings run by Kingfield, Kaizen, SAGA, Provis, Strata Global; no modification service listed
- Dubai Land Department, frequently asked questions (read 01.11.2026) — management company approved by RERA manages common parts; service-charge invoices issued through Mollak
- Law No. (6) of 2019 Concerning Ownership of Jointly Owned Real Property in the Emirate of Dubai, Art. 16, 39, 42 — building rules bind owners and tenants; structural and external changes need the master developer, DLD and the permitting authority; disputes go to the Rental Disputes Settlement Centre