Fit-out contractor contract: what to check before you sign

Scope and drawings, specification, stage payments and retention, variations, defects period, insurance and damage to neighbours. A checklist for renovation contracts.

Librae Academy editorialUpdated

A renovation contract protects you only if it says, in writing, what will be built, from which drawings and materials, for how much, paid when, and what happens when something changes or goes wrong. Before you sign, check seven things: scope tied to named drawings and an estimate, a material specification, stage payments with part held back, a written variation procedure, a defects period with a response time, insurance for the works and third parties, and who obtains the NOC and permits. Most disputes at the end of a renovation trace back to one of these left blank.

#The typical situation

You have a quotation from a fit-out contractor: a page or two of lump sums per room, "supply and install", an advance of some size, and a few lines of terms. In a UAE tower you also have the developer's or community's NOC process ahead (see developer NOCs). The contractor wants to start next week.

The quotation is a contract once you sign it, but it rarely answers the questions that cause trouble: which tiles at what price, what happens when you change the kitchen layout, when you pay and against what, and who fixes the leak six months later. Add a short contract or an annex that does.

#1. Scope: drawings and estimate by version

  • Name the documents. "Works as per drawings A-01 to A-06, rev. 2, and estimate no. 14 dated …". If the contract says only "renovation of apartment 1203", "finished" means whatever the contractor says.
  • List what is excluded. Furniture, appliances, AC units, permits, waste removal, cleaning. Exclusions are where extras come from.
  • Say who gets the NOC and building permits, and who pays the fees and the deposit. Developers ask for the contractor's trade licence in the application, so the contractor has to cooperate either way.
  • Attach the programme. Start date, duration, main stages, and what happens if the date slips.

#2. Specification

For every material that matters, write the type, size, grade and either a product or a price allowance:

ItemWeakGood enough
Floor tiles"Porcelain tiles""Porcelain 60×120, rectified, supply price up to AED X/m², client selects"
Paint"Painting""One primer, two finish coats, washable matt in wet rooms"
Waterproofing"Bathroom waterproofing""Liquid membrane on floor and walls as per drawing, flood test before tiling"
Electrics"Electrical works""New circuits per drawing E-01, test certificate on completion"

If a price is only an allowance, label it as such: "provisional sum". The final cost then follows what you choose, up or down, and the contract should say so.

#3. Payments: stages, checks and what is held back

Under UAE civil law you pay on delivery unless the contract says otherwise. Stage payments, an advance and a retention exist only if you write them in. A schedule that works:

  1. A modest advance that matches what the contractor spends before the first stage, such as materials ordered for you.
  2. Stage payments tied to finished, checked stages: demolition and first fix with the pipes tested, walls and ceilings closed, waterproofing tested and tiling, finishes.
  3. A payment on completion against a closed snag list and the test records (see the renovation snag list).
  4. A retention, a part of the price you keep until the end of the defects period.

The law sets no percentage for the advance or the retention, so write your own. Whatever you choose, the contract must say what "stage finished" means and who confirms it. If you hire independent quality control, name the supervisor's sign-off as the condition for each stage payment.

#4. Variations

Changes are normal. Unpriced changes are the problem. The clause should say:

  • Every change in scope is a written variation with a description, its price and its effect on the programme.
  • Signed or confirmed in writing before the work is done. A message that says "OK" to a stated price counts; a phone call does not.
  • Who can order a variation. You, not the site lead, not the building FM.
  • Omissions reduce the price by the estimate rates.

The new UAE Civil Transactions Law backs this up. Under a fixed price for an agreed design, the contractor cannot ask for more because materials or labour went up. For a change or addition to the design it gets more only if you caused the change, or you authorised it and agreed the extra price. A written, priced variation is that agreement.

#5. Defects period and warranty

  • The law does not set a short defects period for finishes. UAE law makes contractor and engineer liable for 10 years only for collapse and defects that threaten the structure or safety. Everything else is what your contract says.
  • Write the period during which the contractor comes back to fix defects, starting from completion.
  • Write the response time. For example, an active leak at once, other defects within an agreed number of days.
  • Product warranties for appliances, fittings and waterproofing materials are handed over in your name.
  • Link the retention to the period. You release it when the period ends and the defects list is closed.

#6. Insurance and damage to neighbours

A renovation in a tower can damage more than your flat: a leak into the flat below, a scratched lift, a cracked corridor floor.

  • Ask for a policy that covers the works and liability to third parties for the contract period. Check whose name is on it, the amount and the dates.
  • In UAE buildings this is often required anyway. DAMAC lists the contractor's third-party insurance among the fit-out documents. Dubai Holding communities want insurance for the works before they start, and the contractor must insure its own workers.
  • Write that the contractor repairs or pays for damage its work causes to neighbours and common areas. The law already makes the contractor liable for damage from its work, but your deposit is at risk first. Emaar, for example, holds the deposit against damage to common areas by the contractor.
  • If water does reach a neighbour, the steps are in a leak from the flat above, seen from the other side.

#7. Licence, people and building rules

  • The contractor's trade licence must cover the work. Developers ask for it in the NOC application. How to check it is in checking a contractor's licence. In Dubai, electrical work that DEWA has to approve, such as extra load or a new board, is filed by a DEWA-enrolled contractor.
  • Building rules (hours, noise, lift booking, waste) are part of the contract. The contractor follows them and pays any fines it causes.
  • Sub-contractors are the contractor's responsibility, not yours. The law lets the contractor sub-contract unless your contract forbids it, and it stays liable to you for their work. If you want to approve who comes on site, write it in.

#One agreed version in Librae

Most of this checklist is easier when the scope is one document. In Librae you plan the flat, get quantities and a first estimate line by line with demolition, waste removal and 5% VAT, and invite a contractor whose licence Librae has checked. The contractor sees the same plan and estimate, inspects the flat, and agrees the estimate and programme with you. It can propose changes but cannot edit your plan, and the agreed version is issued "For works" with a number. That number is what your contract refers to, so "what was agreed" has one answer. In the UAE you can add independent site supervision to the same order.

#What goes wrong

  • Signing a one-page quotation as the whole contract. No drawings, no specification, no variations clause.
  • A big advance on day one. You lose your main lever before any work is done.
  • "Porcelain tiles" with no size or price. You get the cheapest ones on the market.
  • Changes agreed on the phone. The bill at the end is higher than anyone remembers.
  • No defects period and no retention. After the last payment, a callback is a favour.
  • No insurance, or a policy that expired mid-job. The neighbour's ceiling becomes your cost and your deposit.
  • Nobody named for the NOC. Works stop at the lobby on day one.

#How to check the work

  • The contract names drawings and the estimate by number and revision.
  • Exclusions are listed.
  • Main materials have type, size and price or allowance; provisional sums are labelled.
  • Payments follow checked stages; the condition for each is written.
  • A retention and a defects period are written, with a response time.
  • Variations are written, priced and confirmed before the work.
  • Insurance for the works and third parties is attached and in date.
  • Who obtains the NOC, permits and pays the deposit is stated.
  • Test certificates and as-built drawings are listed as deliverables before the last payment.

#When to call a professional

  • A lawyer for a large villa job, or before signing a contract written in a language you do not read well.
  • A consultant or engineer when the work touches structure, adds area, or needs an authority permit.
  • An independent supervisor to check stages before you pay for them.

#In the UAE

  • The new Civil Transactions Law applies to contracts made from 1 June 2026. It does not reach back, so older contracts stay under the 1985 law.
  • The developer's or community's NOC asks for the contractor's licence, often insurance, and a deposit (see developer NOCs and renovation permits). Make sure the contract says which side provides each.
  • Management inspects at the end before the deposit comes back. Dubai Holding communities inspect within about 21 days and give 30 days to fix anything that does not match the approval. Put the contractor's duty to fix such items into the contract.
  • If you withdraw before the work is finished, the law lets you, but you pay the contractor's costs, the work done and the profit it would have made; a court may reduce the lost profit. A written termination clause is cheaper.

#What the codes say

  • UAE Civil Transactions Law (Federal Decree-Law 25/2025), in force 1 June 2026: standard of work and notice to fix defects, Art. 818; liability for damage, Art. 819; 10-year liability, Art. 821; 3-year limit, Art. 824; payment, Art. 826–827; fixed price and design changes, Art. 829; sub-contractors, Art. 832; employer's withdrawal, Art. 836; no effect on earlier contracts, Art. 4.
  • Dubai Holding Community Management rules (2026): insurance, §8.1.14 and §8.1.30; completion inspection, §8.1.40.
  • Emaar Home Modifications fact sheet (2022) and Emaar FAQ: NOC documents; deposit.
  • DAMAC fit-out work authorisation form: contractor's licence and third-party insurance.

This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.

Sources

  1. Federal Decree-Law No. 25 of 2025, UAE Civil Transactions Law, issuing Art. 2–3 and Art. 4, 818, 819, 821, 824, 826, 827, 829, 832, 836 (official Arabic text, published by Dubai Municipality) — Repeals the 1985 law and is in force from 1 June 2026; does not apply to earlier transactions (4). Standard of work and notice to fix defects (818); liability for damage from the work (819); 10-year liability for collapse and defects threatening the building's soundness and safety (821); claims barred 3 years after the collapse or discovery (824); payment on delivery unless agreed otherwise, and for completed parts of unit-rate work after inspection and acceptance (826–827); fixed price for an agreed design not raised for higher material or labour costs, extra for design changes only if caused by the employer or authorised by it with the increase agreed, court may rebalance after general exceptional events (829); sub-contractor allowed unless the contract forbids it, main contractor stays liable (832); employer may withdraw before completion, paying expenses, work done and lost profit, which the court may reduce (836).
  2. Emaar, Home Modifications fact sheet (2022) — NOC documents start with the contractor's or consultant's Dubai trade licence and a detailed scope of works.
  3. Emaar, FAQ, Home Modifications and NOC — Security deposit protects common areas against damage by the contractor; refunded after a successful inspection.
  4. DAMAC, fit-out work authorisation form — Contractor's trade licence and third-party insurance among the required documents.
  5. Dubai Holding Community Management, Community Rules and Regulations, 1 October 2026, §8.1.14, §8.1.30, §8.1.40 — Insurance for the works before commencement; contractor insures its personnel; completion inspection within about 21 days, 30 days to remedy.
  6. DEWA Regulations for Electrical Installations, 2017 edition, §1.4 and §1.14 — Electrical contractors enrol with DEWA; extensions and alterations need DEWA's prior approval, applied for by an enrolled contractor.