Developer defects liability in the UAE: the 1-year and 10-year rules

What a UAE developer must still fix after handover, for how long, how to report a defect so it counts, where to escalate in Dubai, and how a renovation can affect it.

Librae Academy editorialUpdated

A UAE developer does not walk away at handover. In Dubai the developer must repair or replace faulty installations — electrics, plumbing, drainage, AC and the like — for 1 year from handover of your unit, and fix structural defects for 10 years from the building's completion certificate. No contract clause can shorten either period. To use the guarantee, report each defect in writing through the developer's official channel while the period runs, keep photos and dates, and do not let your own renovation blur who caused what.

#What the developer still owes you

What failedWho answersFor how longFrom when
Installations: wiring, sockets and boards, pipes and valves, drains, sanitary fittings, AC units and drains (Dubai)Developer1 yearHandover of your unit
Structural parts: frame, slabs, load-bearing walls (Dubai)Developer10 yearsBuilding's completion certificate
Collapse, or defects that threaten structure or safety (whole UAE)Engineer and contractor, jointly10 yearsDelivery of the building to the developer

What the table means in practice:

  • Delaying handover does not move the start. If you put off taking possession, the year runs from the completion certificate anyway.
  • Finishes are a grey zone. A cracked tile or a door that drops on its hinges is neither an installation nor structure. Your best protection is the snag list signed at handover (handover and snagging); after that, it depends on your purchase agreement (SPA).
  • Appliances supplied with the flat usually have their own manufacturer warranties. Look in your handover pack.
  • Common parts are not your unit. Risers, shared drains and pipes serving more than one flat, the facade and the structure are common parts. Your unit includes floors, ceilings and the void above them, internal walls that are not load-bearing, windows, doors, bathrooms and the connections that serve only your flat.

#How to report a defect so it counts

  1. Use the official channel. The developer's customer care app, portal or e-mail. Get a ticket or reference number.
  2. Describe it like a snag. Room, item, what is wrong, since when. "Master bathroom, water stain on the ceiling under the shower of the flat above, growing since 3 March" gets a visit; "leak" gets a question.
  3. Attach photos and a video with the date visible or in the file. Take them before anyone opens anything.
  4. Stop the damage. Close the isolation valve, switch off the circuit, put a bucket down. Then report. What to do in the first hour of a leak is in leak from the flat above.
  5. Let them in and record the visit. Who came, what they found, what they did. Ask for the finding in writing if they say "not covered".
  6. Follow up in writing if nothing happens. Keep every message in one thread.
  7. Do a full walk-through before the year ends. Run every tap, drain, AC unit, socket and circuit. Report everything you find in one dated list.

#When the developer will not fix it

Stay in writing at every step and keep the dates.

  • Building management and the owners committee. If your building has an owners committee, it receives owners' complaints about common parts, passes them to the management entity and, if management does not deal with them within 14 days, to RERA. It also reports defects in the building's structure. This route suits defects in common parts and anything that affects several flats.
  • RERA. It considers complaints against developers and management entities about maintaining and repairing common parts. Its online complaint system does not deal with financial claims, contract disputes or compensation, and does not consider transactions older than six months.
  • The Rental Disputes Settlement Centre. Dubai's jointly owned property law sends disputes about the rights and duties it creates, the developer's guarantee included, to this centre. Claims there begin with conciliation.
  • A lawyer for a claim under your purchase agreement, for compensation, or for a structural defect. Under UAE law a 10-year claim must be brought within 3 years of the collapse or of finding the defect, so do not sit on it.

#Your renovation and the guarantee

The year after handover is when most owners renovate. Do it in a way that keeps the guarantee usable.

  • Close the developer's snag list first. Whatever is open at handover, get it fixed or at least logged before your contractor arrives.
  • Get the NOC and stay inside it. Emaar warns that works outside its guidelines may cost you the defect liability warranty, and may block resale and the title deed (developer NOCs).
  • Leave the developer's installations alone where you can. If your plumber moves a pipe and it later leaks, the developer will say the fault is your plumber's, and the law counts your modifications as part of your unit. Emaar does not allow apartment owners to relocate or cover MEP and fire systems at all.
  • Photograph everything before work starts, especially ceilings, wet areas, AC units and the electrical board.
  • Report developer defects found during works at once, before your contractor covers them.

If you renovate during the guarantee, plan the job in Librae. The contractor you invite works from the same plan and estimate as you, and the version you both agree is issued "For works" with a number. That gives you a numbered record of what your contractor was meant to change, which helps when the developer says a fault came from your works. A planned job with a fixed scope also makes the NOC application easier to write. More on timing in renovating right after handover.

#What goes wrong

  • Reporting by phone. No ticket, no date, no proof the developer knew within the year.
  • Waiting for the year to end and finding the AC drain and the shower leak in month thirteen.
  • Letting your contractor fix the developer's defect. You pay, and it becomes hard to hold the developer to that part afterwards.
  • Covering a defect before it is inspected. New tiles over a wet screed hide the evidence.
  • Unapproved works that give the developer a reason to refuse.
  • Mixing up common parts and your unit. A leaking riser is management's job; a leaking pipe under your basin is yours or the developer's, depending on the year.

#How to check the work

  • Handover date and completion certificate date written down.
  • Signed handover snag list in your files, and how it was closed.
  • Every defect reported through the official channel, with a reference number.
  • Photos, videos and visit notes kept with dates.
  • Full walk-through done and reported before the year ends.
  • NOC obtained before any renovation; scope kept.
  • Developer's installations photographed before works and left untouched where possible.

#When to call a professional

  • A leak-detection company if the developer and you disagree on where water comes from. Ask for a written report that names the source and the method.
  • An electrician registered with DEWA to test a circuit the developer says is fine.
  • A structural engineer for cracks that grow, run across walls, or come with doors and windows starting to jam.
  • A lawyer before the year ends if the developer refuses in writing, and at once for structural defects.
  • Independent quality control if you renovate in the guarantee year and want hidden works checked before they are closed.

#In the UAE

  • Outside Dubai the federal 10-year rule for collapse and structural safety applies. For installations and finishes, read your SPA and the emirate's property law, and ask a lawyer if the sum matters.
  • Buildings delivered before 1 June 2026. The new Civil Transactions Law is not retroactive, so the 10-year rule for such buildings may still come from the 1985 law. The periods are the same in substance; which law applies is a lawyer's question.
  • Who you claim against. The federal 10-year rule binds the engineer and contractor to whoever ordered the building, usually the developer. In Dubai your own claim for structural defects is against the developer, under the jointly owned property law.

#What the codes say

  • Dubai Law No. 6 of 2019 (jointly owned real property): what a unit includes, Art. 9; owners committee duties, Art. 24(4) and 24(6); RERA complaints, Art. 33(a)(4); developer's 10-year and 1-year liability, Art. 40; disputes to the Rental Disputes Settlement Centre, Art. 42.
  • UAE Civil Transactions Law (Federal Decree-Law 25/2025): 10-year liability, Art. 821; exemption clauses void, Art. 823; 3-year limit, Art. 824; no retroactive effect, Art. 4.
  • Dubai Land Department, RVS complaints: scope and six-month limit.
  • Emaar Home Modifications fact sheet (2022): loss of the defect liability warranty for works outside the guidelines.

This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.

Sources

  1. Dubai Law No. 6 of 2019 on jointly owned real property, Art. 2, 9, 24, 33, 40 and 42 — What a unit includes (9); owners committee passes complaints to management and to RERA after 14 days, and reports structural defects (24(4), 24(6)); RERA considers complaints on maintenance of common parts (33(a)(4)); 10 years structural from completion certificate, 1 year installations from handover, contrary agreements void (40); Rental Disputes Settlement Centre hears disputes under the law (42).
  2. Federal Decree-Law No. 25 of 2025, UAE Civil Transactions Law, Art. 4, 821–824 — In force 1 June 2026, not retroactive (4). Engineer and contractor jointly liable 10 years from delivery for collapse and defects threatening structural integrity and safety (821); exemption clauses void (823); claims within 3 years of collapse or discovery (824).
  3. Dubai Land Department, Complaint against a real estate company (RVS) — Not for financial claims, contract-term disputes or compensation; transactions older than six months not considered; response within 5 working days.
  4. Emaar Community Management, Home Modifications fact sheet (2022), archived copy — Modifications not following the guidelines may mean loss of the defect liability warranty; in apartments no removal of the existing tiles and no relocating or covering MEP and fire-fighting systems.

Читать по-русски