Renovating a new off-plan flat after handover: what to do first

What to change in a new UAE apartment before you move in, in what order, and how to renovate without losing the developer's 1-year warranty on installations.

Librae Academy editorialUpdated

Renovate a new off-plan flat in this order: inspect and get the developer's snags fixed, plan the whole job, get the NOC, then do the dusty and wet work before you move in. In Dubai the developer must repair faulty installations for 1 year from handover, so keep that year usable. Log every developer defect before your contractor starts, leave the developer's pipes, drains, AC and wiring alone where you can, and stay inside the approved scope. Emaar, for one, warns that works outside its guidelines may cost you the defects warranty.

#The order that works

  1. Handover inspection. Walk the flat with the developer's representative and get every defect on a signed list (handover and snagging).
  2. Utilities on. DEWA and the cooling account. You need power, water and AC to test anything.
  3. Developer's fixes. Get the list closed, or at least each item logged with a reference number and a date.
  4. Measure and plan the whole job. Floors, wardrobes, lighting, ceilings, kitchen, bathrooms, paint, curtains. One plan, one scope.
  5. Quotes on that plan. Contractors price the same scope, so you can compare them.
  6. NOC and entry permits. One application for the whole scope, through your developer or community management. In an Emaar building that is the Emaar Community Management portal (ecm.ae), with a refundable deposit; you do not apply to the DDA for an ordinary flat fit-out (developer NOCs).
  7. Works, in the right sequence: first the work that goes inside walls and ceilings, then finishes (order of works).
  8. Management's completion check and your own snag list for the contractor (renovation snag list).
  9. Move in.

#What to do before you move in

Some jobs are cheap to do in an empty flat and miserable once you live there.

JobBefore moving inWhy
Flooring over the developer's tilesYesFurniture out, doors trimmed once
Built-in wardrobes and storageYesDust, noise, several site days
Ceilings, extra downlights, tracks, cove lightingYesCutting boards, dust everywhere
Curtain pockets and blind recessesYesPart of the ceiling work
Kitchen changesYesNo kitchen for days or weeks
Bathroom changesYes, if anyWet works and curing time
Paint in new coloursYesEmpty rooms, faster and cleaner
Smart switches and sensorsCan waitMostly swap-in, little dust (smart home in a new flat)
Loose furniture, art, rugsAfterNo permit, no dust

Think twice about bathrooms and kitchens in a brand-new flat. They are where most developer installations sit: pipes, drains, waterproofing, extraction. Replacing a new vanity or worktop is one thing. Moving a WC, a shower drain or a sink means touching the developer's work, and in Emaar apartments relocating MEP is not allowed at all.

#How to keep the developer's warranty

  • Developer first. Every developer defect logged, with a reference, before your trades arrive.
  • Photograph everything the day before works start: ceilings, wet areas, AC units, the electrical board, the water heater, every wall.
  • Stay inside the NOC. Emaar lists the consequences of works outside its guidelines: possible loss of the defect liability warranty, problems with resale and the title deed, and violation notices.
  • Do not remove the original tiles in an Emaar apartment. Emaar bans it; new tiles may go over the old ones. Check your own building's rule before choosing a floor.
  • Do not move, remove or box in pipes, drains, AC units or fire devices unless your NOC allows it. Emaar does not allow it in apartments.
  • Keep your contractor away from the developer's defects. If your plumber "just fixes" a developer leak, you pay, and it becomes hard to hold the developer to that part afterwards.
  • Know what becomes yours. Under Dubai law the fixtures you install and the changes you make become part of your unit. If a pipe your plumber moved leaks, expect the developer to refuse it; your claim is against your contractor.
  • Report anything the works uncover, such as a damp patch behind a removed panel, to the developer at once, before it is covered.

More on what the developer owes you and for how long is in developer defects liability.

#If you will let the flat

Do anything that touches services and ceilings before the first tenant moves in. Under Dubai's tenancy law a tenant may not alter the flat without your consent, and once someone lives there you will be arranging works around them and the building at the same time (renovating a rented flat). During the warranty year your tenant reports faults to you and you report them to the developer, so ask for photos and dates with every report.

#Plan it before the keys

Most of the waiting after handover is not the NOC but deciding what you want and getting a price you trust. You can do that before the keys. In Librae you draw the flat from the developer's floor plan in your sales pack, and confirm the dimensions with a tape or an iPhone LiDAR scan at the handover inspection. Furniture, finishes and lighting go on the same plan in 2D and 3D. Librae computes the quantities from it, then a first estimate line by line with demolition, waste removal and 5% VAT. A contractor invited from the project sees the same plan and estimate, checks them on a free site visit and agrees the price and schedule with you; they can propose changes but cannot edit your plan. Contractors in the Librae directory are listed only after Librae checks their licence. The agreed version, issued "For works" with a number, is also a clear scope for the NOC application. In the UAE you can add independent quality control when you order the renovation through Librae, so hidden works are checked before they are closed.

#What goes wrong

  • Starting before the snags are closed. The developer then blames your contractor for every crack and leak.
  • Ripping out the developer's tiles in a building that bans it.
  • Moving a drain or a WC "a little". Expect the developer to refuse warranty claims on that part, and the risk of a leak into the flat below is now yours.
  • Applying for the NOC piece by piece. Each extra item is another application and another wait.
  • Moving in first and renovating later. Dust in the AC, furniture moved twice, weeks without a kitchen.
  • No photos of the original state. Later you cannot show what the developer handed over.

#How to check the work

  • Handover snag list signed; every item fixed or logged with a reference.
  • Whole-flat plan and one scope agreed before quotes.
  • NOC received, scope matches the plan; entry permits issued.
  • Photos of the original state taken before works.
  • Developer's pipes, drains, AC and fire devices untouched or changed only as the NOC allows.
  • Pressure, flood and electrical test records collected for anything your contractor changed.
  • Management's completion check passed; deposit refund requested.
  • A full walk-through planned before the developer's year ends.

#When to call a professional

  • A fit-out contractor with a Dubai trade licence, which Emaar asks for in the NOC application. Check the licence before you sign.
  • An electrician registered with DEWA for any new circuit, and a test certificate at the end (electrical testing).
  • A designer if you change the kitchen layout, ceilings and lighting together and want them to fit on one plan.
  • Independent supervision if you will not be on site or the job includes bathrooms or ceilings (quality control during the works).

#What the codes say

  • Dubai Law No. 6 of 2019 (jointly owned real property): what a unit includes, including occupant's fixtures and modifications, Art. 9(a); developer's 1-year and 10-year liability, Art. 40.
  • Emaar Home Modifications fact sheet (2022): works without NOC, apartment prohibitions, processing time, entry permits, consequences of works outside the guidelines.

This guide explains good practice and cites the documents listed below. It is not a permit, a design approval or an engineering opinion. Work on electrical, gas, fire-safety and structural elements must be carried out by licensed professionals and approved by the relevant authority.

Sources

  1. Dubai Law No. 6 of 2019 on jointly owned real property, Art. 9 and 40 — Developer liable 1 year from handover for defective installations and 10 years from the completion certificate for structural defects; contrary agreements void (40). Fixtures installed by the occupant and later modifications are part of the unit (9(a)).
  2. Emaar Community Management, Home Modifications fact sheet (2022), archived copy — Works needing no NOC; apartment prohibitions (walls, removal of existing tiles, MEP and fire systems); 3 business days for minor and major NOCs; entry permit for every contractor; documents; loss of defect liability warranty for works outside the guidelines. Applications today go through the ECM portal (ecm.ae).